"Sun Energy" LLC, Armavir Province, Merdzavan village

Capacity:

3000 kW

Location:

Merdzavan, Armavir Province

Solar modules՝

AE SOLAR 450 W, monocrystalline 6820 pcs, Germany

Inverter:

Huawei 100 kW inverter, 30 pcs.

Annual electricity production։

5550 MWh

Description
 

The installation of 3 MW power plant was made with 60 blocks (inverters). The Power plant is equipped with accident-prevention  systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. 
In the surrounding area must be installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits. The generated capacity is transferred to the "Spandaryan" substation.

 

Voskanyan Group 115.5 kW
Voskanyan Group
"Voskanyan Group" LLC, producer of cans, will use the inexhaustible energy of the sun from now on, saving 𝟖,𝟖𝟑𝟓,𝟎𝟎𝟎 AMD
115.5 kW
MOUSSALER PRINTING HOUSE 510 kW
MOUSSALER PRINTING HOUSE
The installation of 510 kWt power plant was made more than 1300 solar panels. The Power plant is equipped with accident-prevention  systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures
510 kW
ARPI KINDERGARTEN 6,56 kW
ARPI KINDERGARTEN
Բարեգործական ծրագրի շրջանակում ամեն տարի մի քանի տասնյակ կրթական հաստատություններ անցում են կատարում արևային էներգիային։
6,56 kW
"GAVA" LLC, Aragatsotn province, Ashtarak 28.5 kW
"GAVA" LLC, Aragatsotn province, Ashtarak
28.5 kW