"Module Sun" LLC, Gegharkunik Province, Mets Masrik village

Capacity

3500 kW

Location

Gegharkunik Province, Mets Masrik village

Solar modules

Longi Solar 535 W, bifacial, monocrystalline 6550 pcs

Inverter

Huawei 215 kW inverter, 14 pcs

Annual electricity production

6330 MWh

Description

 

The installation of 3․5 MW pick power (3 MW nominal power ) plant was made with 14 blocks (inverters). The Power plant is equipped with accident-prevention  systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits.

 

Kotayk province, v. Ara 5.28 kW
Kotayk province, v. Ara
5.28 kW
"Sun Energy" LLC, Armavir Province, Merdzavan village 3000 kW
"Sun Energy" LLC, Armavir Province, Merdzavan village
The installation of 3 MW power plant was made with 60 blocks (inverters). The Power plant is equipped with accident-prevention systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits. The generated capacity is transferred to the "Spandaryan" substation.
04 Dec 2020
3000 kW
Saralanj Basic School 25,42 kW
Saralanj Basic School
25,42 kW
Armavir province, Metsamor 5.32 kW
Armavir province, Metsamor
5.32 kW